Friday, May 30, 2008

Ready For Stucco


The lath for the stucco is complete ready and waiting for inspection from the Sonoma County Building Inspector. In addition to stucco being applied to the MacPhail's Winery roof insulation will continued to be installed. After the roof insulation, metal roofing.

Friday, May 23, 2008

Finished Look


The finished siding is being installed on the MacPhail's Family Winery. The completed winery siding will be a combination of both stucco and metal finishes.

Wednesday, May 14, 2008

Seeing Green

As you can see most of the wall panels have been installed on the MacPhail’s Family Winery. Yes we are aware of the new improved green construction industry and no the wall panels will not remain their current green color. You need to go to http://www.macphailwine.com/?CFID=158021&CFTOKEN=63903264 and buy James MacPhail’s Pinot Noir and let him know that PCI sent you.


Thursday, May 1, 2008

May Day



The siding is currently being installed at MacPhail’s Family Winery.


James MacPhail has returned from Tokyo where he was hosting winemaker dinners and events to introduce his wines to the Japanese market.

Friday, April 11, 2008

Framing Nearly Completed


Kleinfelder Inc. is on site testing the high strength bolting. You can see the mezzanine is installed.

Wednesday, April 2, 2008

Steel Is In The Air.



The winery is starting to take shape.

Tuesday, March 11, 2008

Here It Is!


The American Building was delivered to the jobsite last Thursday. Ron is on the job checking out all the parts and pieces.