Friday, June 20, 2008

The Stucco is On, Siding On Roofing is Going On



The exterior siding is on the stucco is on and the roof is being installed. All of our subcontractors are coordinated and cooperating in order to complete the MacPhail’s Family Winery on time. Craigie Construction is working on the roofing. Lunardi Electric is busy with the interior electrical, http://lunardielectric.com/. Mitch our on site carpenter has completed the hand made barn doors.

Thursday, June 19, 2008

Because You Asked



Yes we are working on other projects. Currently we are working on the New G. & C. Auto Body, http://www.gandcautobody.com/ . The concrete slab for this project went in with one pour starting at two o'clock in the morning.

Friday, May 30, 2008

Ready For Stucco


The lath for the stucco is complete ready and waiting for inspection from the Sonoma County Building Inspector. In addition to stucco being applied to the MacPhail's Winery roof insulation will continued to be installed. After the roof insulation, metal roofing.

Friday, May 23, 2008

Finished Look


The finished siding is being installed on the MacPhail's Family Winery. The completed winery siding will be a combination of both stucco and metal finishes.

Wednesday, May 14, 2008

Seeing Green

As you can see most of the wall panels have been installed on the MacPhail’s Family Winery. Yes we are aware of the new improved green construction industry and no the wall panels will not remain their current green color. You need to go to http://www.macphailwine.com/?CFID=158021&CFTOKEN=63903264 and buy James MacPhail’s Pinot Noir and let him know that PCI sent you.


Thursday, May 1, 2008

May Day



The siding is currently being installed at MacPhail’s Family Winery.


James MacPhail has returned from Tokyo where he was hosting winemaker dinners and events to introduce his wines to the Japanese market.

Friday, April 11, 2008

Framing Nearly Completed


Kleinfelder Inc. is on site testing the high strength bolting. You can see the mezzanine is installed.